CONSTRUCTION TIMELAPSE DECEMBER 2023 – JUNE 2024
CONSTRUCTION TIMELAPSE DECEMBER 2023 – JUNE 2024
For the main building that will house the private residences and the extensive shared spaces, the tower crane has been installed, basement works are complete and a slab on ground at the base is complete along with rainwater tanks and structural footings. Suspended concrete slabs are now being installed and will continue for the remainder of year, right up until the concrete roof slab is poured. Precast concrete columns and walls are also being installed and the installation of basement services are to commence in coming months.